TEHRAN (NIOC) _ Operator of South
Pars Phase 13 development project said the last platform of the offshore
project was successfully installed in the Persian Gulf. According to the Pars Oil and Gas Company
(POGC), Payam Motamed said Platform 13C was the fourth and last platform of the
project
.
He
said the 2,500-ton satellite structure was installed using an HL5000 barge
.
Having reached 98% completion, the platform was
loaded at the yard of SADRA together with 13A Platform last month using a
Push/Pull method, Motamed said
.
Once
Platforms 13A and 13C come on stream, the phase’s gas output will increase by
28 mcm/d. The phase is developed for 56 mcm/d of gas production capacity
.
|